Weston Aqueduct Supply Main Rehabilitation - Medford, Somerville, Arlington (Contract 6544)

Project type
Water
Project status
Communities
6544 WASM Medford Somerville Arlignton Project - figure1
6544 WASM Medford Somerville Arlignton Project - figure2

About this Project

MWRA’s Weston Aqueduct Supply Main 3 consists of approximately 10 miles of steel pipe installed in the 1920s and 30s. The pipe is a critical supply to over 250,000 customers in the Northern High, Northern Extra High and Intermediate High supply systems serving Waltham, Watertown, Belmont, Lexington, Bedford, Arlington, Somerville and Medford.  It also can provide emergency supply to the Gillis Pump Station serving communities of the North Shore and Northern Intermediate High communities. Figure 1 shows the full extent of the WASM 3 pipeline and the work limits for the current construction contract.

This first construction contract includes rehabilitation of approximately 13,800 feet of 56-inch and 60-inch diameter water main starting in Medford in December 2020, and continuing in Somerville and Arlington from Fall of 2021 to Spring of 2024. The rehabilitation will consist of cleaning and internal cement mortar lining of the pipe and adding valves for better operational flexibility.  Figure 2 shows the segments to be completed under this contract.

The work is restricted to low water demand months from September 15 to May 15, which necessitates three construction phases during the duration of the contract. This work restriction is necessary to ensure the main is operational during high summer demand periods. MWRA has awarded this $19.5 million contract to Albanese D&S, Inc. with a contract term of 912 calendar days from the Notice to Proceed.

Updates

March 29, 2023

  • Starting next week, begin filling portions of WASM 3 for testing
  • Disinfection entire pipeline scheduled for late April
6544 WASM Medford Somerville Arlignton Project
Pleasant Street - Cement Lining Operation
6544 WASM Medford Somerville Arlignton Project
Installation of Catch Basin on Pleasant Street
6544 WASM Medford Somerville Arlignton Project
Welding interior plates over manways

March 2, 2023

6544 WASM Medford Somerville Arlignton Project
Pleasant Street-New Valve and Bypass Piping
6544 WASM Medford Somerville Arlignton Project
Cleaning from Access Pit
6544 WASM Medford Somerville Arlignton Project
Cleaning Machine with rotating scraper arms inside 54” pipe

February 2, 2023

6544 WASM Medford Somerville Arlignton Project
Swan place-new 56 inch steel pipe at access pit
6544 WASM Medford Somerville Arlignton Project
Matching existing steel pipe to new
6544 WASM Medford Somerville Arlignton Project
Prototype –Electrical cement lining machine

December 23, 2022

6544 WASM Medford Somerville Arlignton Project
Contractors installed 6 access pits; Arlington Cement lining operation - cement line: 800 feet
6544 WASM Medford Somerville Arlignton Project
New valve on Pleasant Street - Arlington
6544 WASM Medford Somerville Arlignton Project
WASM Lock bar pipe

November 7, 2022

6544 WASM Medford Somerville Arlignton Project
Arlington access pits
6544 WASM Medford Somerville Arlignton Project
Pleasant street-Arlington

August 9, 2022

6544 WASM Medford Somerville Arlignton Project
Existing Arlington Plaza
6544 WASM Medford Somerville Arlignton Project
Reconstruction of Arlington Plaza
6544 WASM Medford Somerville Arlignton Project
Arlington plaza ribbon cutting

June 29, 2022

Work Update:

  • Work over 3 year duration
  • Rehabilitation of WASM 3- work only allowed from September 15th to May 15th due to demand.

April 28, 2022

Upcoming work:

  • Complete installation of new water main piping at Meter 171
  • Activation of Meter 90 - new flow meter in Somerville
  • Filing of segment 2 in Arlington in preparation for activation of WASM 3
  • Restoration of Arlington plaza
6544 WASM Medford Somerville Arlignton Project
Broadway and Palmer
6544 WASM Medford Somerville Arlignton Project
Broadway and Palmer
6544 WASM Medford Somerville Arlignton Project
Arlington Center - pipe and backfill
6544 WASM Medford Somerville Arlignton Project
Arlington Center - pipe and backfill

March 31, 2022

Update to Work

Upcoming work:

  • Continue closure of access pits along route
  • Complete installation of new water main piping and backfill at Arlington Center
  • Commence surface upgrade of Arlington Plaza area
6544 WASM Medford Somerville Arlignton Project - 02_Page_1
6544 WASM Medford Somerville Arlignton Project - 02_Page_2
6544 WASM Medford Somerville Arlignton Project
Capen Court in Somerville near the Somerville Housing authority.
6544 WASM Medford Somerville Arlignton Project
Installation of new 60- inch steel pipe
6544 WASM Medford Somerville Arlignton Project
Coral Street in Arlington-new pipe, bypass and blowoff
6544 WASM Medford Somerville Arlignton Project
Coral Street in Arlington-new pipe, bypass and blowoff
6544 WASM Medford Somerville Arlignton Project
Installation of new Meter 90 cabinet and McCrometer flow
6544 WASM Medford Somerville Arlignton Project
Activation of portion of WASM3 to feed Meter 80 - Somerville

February 3, 2022

Work Timeline: Work to be done between May 15th to September 15th due to demand

Overview: The rehab of WASM pipeline will increase the flow capacity. This is a critical line and redundant for the tunnel. The pipeline is structurally sound bu some tuberculation has occurred and that will be cleaned.

6544 WASM Medford Somerville Arlignton Project
Testing new 60-inch valves
6544 WASM Medford Somerville Arlignton Project
Coral Street in Arlington (butterfly valve with structure around it)
6544 WASM Medford Somerville Arlignton Project
Removal of existing valve in Arlington center
6544 WASM Medford Somerville Arlignton Project
Capen Court - Somerville

January 5, 2022

Upcoming Items:

  • Excavation and construction of access pit in Arlington Center Plaza
  • Subcontractor will continue cleaning and cement lining of 60 inch steel WASM 3
  • Coordinate with Verizon to complete fiber optic duct bank relocation in Arlington center
  • Begun closure of access pits in Somerville
6544 WASM Medford Somerville Arlignton Project
Steamer
6544 WASM Medford Somerville Arlignton Project
Concrete conveyance

November 3, 2021

Upcoming Items:

  • Excavation and construction of cement lining access pits in Arlington
  • Subcontractor will commence cementlining of 60-inch steel WASM
  • Coordination with Verizon to complete fiber optic duct bank relocation in Arlington Center
  • Somerville Housing Authority plans to demo old MWRA metering on Capen Court
6544 WASM Medford Somerville Arlignton Project
Building access pits at Mystic Shops Building to get access to 60-inch water main
6544 WASM Medford Somerville Arlignton Project
Access pit in Somerville (exposed top of pipe)
6544 WASM Medford Somerville Arlignton Project
Machine inside pipe to clean off tuberculation on Irvington Road in Somerville
6544 WASM Medford Somerville Arlignton Project
Before shot of cut existing pipe with a lot of tuberculation
6544 WASM Medford Somerville Arlignton Project
After shot once cleaned

September 28, 2021

Upcoming Items:

  • Dewatering of the WASM3 pipeline through Arlington and Somerville
  • Coordination with Somerville Housing Authority - access during construction and new building
  • Coordination with Arlington: Broadway Plaza businesses, Verizon duct bank relocation
  • Removing 3 trees in Somerville
  • Preconstruction photos and TV inspection of adjacent utilities in Arlington
6544 WASM Medford Somerville Arlignton Project
Remobilization & Laydown Area
6544 WASM Medford Somerville Arlignton Project
Dewatering area

September 7, 2021

Upcoming Items:

  • Coordination with Somerville Housing Authority - access during construction and new building
  • Coordination with Arlington - Broadway Plaza businesses (making banners)
  • Removing some trees in Somerville
  • MWRA Ops - Reviewing Dewatering Plan for next segment

August 6, 2021

Upcoming Items:

  • Coordination with Somerville Housing Authority
  • Coordination with Arlington
  • Removing some trees in Somerville
6544 WASM Medford Somerville Arlignton Project
Map divided in 3 sections over the next 3 years: 1. 1st section in Medfird complete 2. Arlington & Somerville section next
6544 WASM Medford Somerville Arlignton Project
WASM Activation in May - Testing for PH and Chlorine
6544 WASM Medford Somerville Arlignton Project
Restoration of the ball field (water cannons and continuous rain has helped with restoration)
6544 WASM Medford Somerville Arlignton Project
Restoration of ball field

April 27, 2021

6544 WASM Medford Somerville Arlignton Project
Boston Avenue air valve structure
6544 WASM Medford Somerville Arlignton Project
Dewatering blow off connection
6544 WASM Medford Somerville Arlignton Project
Installation of new steel pipe
6544 WASM Medford Somerville Arlignton Project
Restoration of ball field

March 31, 2021

Work Done To Date:

  • Complete access pits with new steel pipe
  • Restoration of construction areas
  • Disposal of contaminated soil off site
  • WASM3 planning for disinfection/activation
6544 WASM Medford Somerville Arlignton Project
Recent completion of cement lining
6544 WASM Medford Somerville Arlignton Project
Recent completion of cement lining
6544 WASM Medford Somerville Arlignton Project
Cutting existing steel pipe
6544 WASM Medford Somerville Arlignton Project
Arrival of new steel pipe
6544 WASM Medford Somerville Arlignton Project
Installation of new steel pipe
6544 WASM Medford Somerville Arlignton Project
Closure of access pits

March 2, 2021

6544 WASM Medford Somerville Arlignton Project
Cutting 60-inch steel water main in preparation or forthcoming replacement section
6544 WASM Medford Somerville Arlignton Project
Mixing and conveying cement for rehabilitation of the water pipe
6544 WASM Medford Somerville Arlignton Project
Machinery utilized for applying cement lining during rehabilitation of the pipeline
6544 WASM Medford Somerville Arlignton Project
Steam machine for concrete curing

February 3, 2021

Work Done To Date:

  • Rehab of WASM 3 – Work will be conducted from Sept 15 to May 15th due to demand
  • Cleaning and cement mortar lining of approximately 4,870 feet of 56-inch steel water main
  • Cleaning and cement mortar lining of approximately 8,310 feet of 60-inch steel water main
  • Furnishing and installing (4) butterfly valves and appurtenances.
6544 WASM Medford Somerville Arlignton Project
WASM 3 - recent work: Installing Access Pits
6544 WASM Medford Somerville Arlignton Project
WASM 3 - recent work: Installing Access Pits
6544 WASM Medford Somerville Arlignton Project
Removing section of pipe - tuberculation
6544 WASM Medford Somerville Arlignton Project
Removing section of pipe - tuberculation
6544 WASM Medford Somerville Arlignton Project
Cleaning
6544 WASM Medford Somerville Arlignton Project
Rivets connecting pipes