This Project was developed as an interim improvement to enhance MWRA’s emergency response to a failure of the Metropolitan Tunnel system until a redundant tunnel is constructed. The Project is to replace pressure reducing valves on the Weston Aqueduct Supply Main (WASM) 4 at Nonantum Road in Boston and WASM 3 at Mystic Valley Parkway in Medford to increase the supply from the Northern Low Service System and reduce the need to pump non-potable water out of the Spot Pond Reservoir in an emergency. The new larger pressure reducing valves at Nonantum Road and Mystic Valley Parkway will be designed to be controlled remotely through SCADA. The Northern Low Service pipeline would operate at increased grade lines to supply additional flow to the Spot Pond Pumping Station and Storage Facility and the Gillis Pumping Station in an emergency condition with the tunnel system out of service.
The contract will demolish the existing Nonantum Road and Mystic Valley Parkway PRV vault structures, including four 24-inch PRVs and appurtenances, and construct new larger cast-in-place vaults. At Mystic Valley Parkway, two 42-inch PRVs and at Nonantum Road two 30-inch PRVs, isolation valves, piping, and other appurtenances will be installed. Additionally, a new master meter will be constructed at the Mystic Valley Parkway pressure reducing valves and the existing master meter located near the Nonantum Road Pressure reducing valves will be upgraded to accommodate the increased flow.
Work will be sequential, starting at the Mystic Valley Parkway PRV Vault, followed by the Nonantum Road PRV vault. Construction is nearing completion.
Project Updates
Sign up for electronic project notifications and updates through our Everbridge service.
Image
Working on grating within the vault
Image
W16 Venturi Meter Chamber installation
Image
New Venturi Site Restoration
Image
W16 - Installing supports for top slab
Image
Roof slab decking in place, installing rebar
Image
W16 - installing new steel pipe west of the vault
Image
W14 - Cabinet installation
Recently Completed:
Pressure tested valves and piping at W14
Continued rebar, forms and placing concrete at W16
Upcoming:
Complete fill at W14 for visual inspection of closure piece and complete backfill
Continue concrete work at new W16 vault
Image
W16 - Placing concrete for the east wall of the PRV vault
Image
W16 east wall forms removed
Image
W14 - Interior view of cement mortar lining
Image
W14 - Ductbank and equipment and concrete placement
Image
W14 - Rough Grading
Recently Completed:
Installed valves and started backfilling at W14
Installed rebar and started placing concrete at W16
Upcoming:
Conduct pressure test of pipe and valves at W14
Continue concrete work at new W16 vault
Image
W14 Temporary 48” Blind Flange installed at Station 64+54.5
Image
W14 8’” Bypass at Station 64+29.2
Image
W14 Concrete Placed for the Thrust Block at Station 64+51.5
Image
W14 Backfilling and installing cathodic protection
Image
Image
W16 Placing Concrete for the North Wall of the PRV Vault
Image
W16 steel work under the tarp
Recently Completed:
Completed W14 pipe and PRV installation
Completed ductbanks at W14
Started Demo at W16
Upcoming:
Complete butterfly valve installation at W14
Continue with new vault at W16
Image
W14 PRVs Installed
Image
W14 Outside Piping
Image
Applying tape at welded joints at W14
Image
W16 Demo of existing PRV vault
Image
Screening was pulled back to improve sightlines for vehicles exiting parking lot.