Breadcrumb Home Update for Nut Island Headworks Odor Control and HVAC Improvements Project (Contract 7548)  
 Update for Nut Island Headworks Odor Control and HVAC Improvements Project (Contract 7548)  Address
Nut Island facility
  Exterior view of Odor Control roof and site
   About this Project The Nut Island Headworks Odor Control and HVAC Systems Improvements project involves an extensive rehabilitation of the facility that will ensure that Nut Island continues to work as designed.  Odor Control facility access, fuel tank replacement and other appurtenances will be rehabilitated.  This project will take approximately 36 months to complete.In January 2020, this $187,410.85 contract was awarded to Walsh Construction.
The first phase of work will begin on Tuesday, April 21, 2020.  The work involves the installation of erosion controls (silt fencing and straw waddles), catch basin inlet protection, tree protection, temporary chain link fence and concrete barriers delineating work zones.  The initial work will be followed by establishing a temporary construction laydown area.  Once these activities are complete, the next phase of work will begin in May at the Nut Island facility.
Public Access Plan Public Access paths will remain open during construction.  Please obey all posted signage on site.
Contact If you have any questions please contact MWRA Public Affairs.
Updates Sign up for electronic project notifications and updates through our Everbridge service .
July 11, 2023   Perforated Pipe and Crushed Stone Trench Drain
     Roof waterproofing transition
     Carbon Adsorber (CAD) 2 Fiber Reinforced Plastic (FRP) 90 degree elbow
     Parking lot mill and overlay
    Previous  1  of   Next    Loading Carbon into new Carbon Adsorber Unit (CAD) System
     Odor Control Roof Panel Placement
     Odor Control Roof Surfacing
     Odor Control Roof Insulation
     Stair 12 near bench shaft
     Sidewalk Repair adjacent to Emergency Spillway
    Previous  1  of   Next    Layout of all CAD (Carbon Adsorber) vessels
     Catwalk access to wet scrubbers and dampers
     Screening Room Odor Control Fiber Reinforced Plastic (FRP) Replacement
    Previous  1  of   Next    Fiber Reinforced Plastic (FRP) duct
     Carbon Adsorber Inlet and Outlet Ducts
     Carbon Adsorber Power and Controls
     Generator Room Air Handling Unit (AHU) replacement
    Previous  1  of   Next    All carbon vessels delivered and being set in place
     CAD #9 & 10 Inlet and Outlet ducts
     CAD #1 and 2 topping slab
     Odor control roofing to resume in the spring
     FRP Duct and grease filters in grit room
    Previous  1  of   Next    CAD foundations and topping slab
    Previous  1  of   Next    CAD area topping slab demolition to build new foundation
    Previous  1  of   Next    Masonry work has begun on Stair 12 super structure
     The wet scrubber testing (pH & ORP probes)
     Supply air duct in Odor Control Room
      Odor Control roof with temporary removable panels over carbon adsorbers
     Hot water piping in screen room in AHU-5 & 6
    Previous  1  of   Next    Constructing stair 12 Masonry and tie into existing bench structure
    Previous  1  of   Next    Odor Control Stainless FRP Duct
     dor Control FRP Duct Installation
     Wet Scrubber Rehab and Chemical Pumps
     Odor Control Fan #2 (fan and damper controls)
     AHU-3 & 4 rigging (Truck Bay hatch hoist)
    Previous  1  of   Next    Odor Control Stainless Steel Duct Installation
     Odor Control FRP Duct Installation
     Wet Scrubber Rehab (Chevron Mist Eliminators, spray nozzles and media)
     Stair 12 at ground level. Masons will begin building a stair tower.
     Air Handler Replacement (AHU- 1 & 2) will serve pump and blower room
    Previous  1  of   Next    Odor Control Duct Installation at Wet Scrubbers
     Air Handler Replacement (Pump & Blower Room)
    Previous  1  of   Next    Odor control fan #1 and 2 pads
     Wet scrubber & 90-inch Duct Demo
     Elevated walkway platform (access to dampers and controls)
     8-inch Sanitary Ejector Piping
    Previous  1  of   Next    New fuel oil tanks in service
     Odor Control Fan Headers (new fan on left, old fan on right)
     Caustic storage tanks and pumps
    Previous  1  of   Next    Utility relocation at Stair 12 (Building code requires new egress path)
     HVAC duct replacement in Grit Area
     Underground fuel oil tank piping and wiring
     Breeching for new boilers
    Previous  1  of   Next    Setting one of the 20,000 Fuel Oil Storage Tanks
     20,000 Gallon Underground Fuel Oil Storage Tanks in place
     Odor control duct being rigged into the odor control room
     Wet Scrubber #3 Inlet Duct fitup
     Carbon absorber #1 demolition
    Previous  1  of   Next    Temporary OC Duct (preliminary testing to test flow for changes)
     Temporary Supply Air Fans
     Excavation for new underground storage tanks
    Previous  1  of   Next    Portable CAD Unit (ductwork outside)
    Previous  1  of   Next    Fan 4 intake (suction) prior to installation of additional Odor Control Duct
     Exhaust from fan 4 as it enters the header
     Odor control room (future hypochlorite location)
     Sub-contractor prep work to get fan up and running
     New stainless steel ducts in grit level
    Previous  1  of   Next    Odor Control Fan #4 set in place & grouting base frame
     New Odor Control SCADA cabinet set in pump and blower room
     New caustic tanks set in place
     Chemical fill piping for sodium hypochlorite and sodium hydroxide
     Temporary carbon absorber unit
     HVAC duct work in screen room
     Work at spillway, finishing grouting rails and planning stop logs
    Previous  1  of   Next    Stop log frames being installed in the emergency spillway. There is a yellow crane hauling some logs.
     Stop log frames being installed in the emergency spillway. Workers installing structures at spillway.
     90-inch odor control fan header installed
     Forms for new odor control dan foundation
     Caustic storage tanks delivered and stored on site
    Previous  1  of   Next    Temporary Ductwork at grit level
     Temporary duct system to provide ventilation while existing ductwork gets replaced
     Temporary fans to provide ventilation while air handlers get replaced
     Outdoor roof and removable covers and ductwork being delivered to site
     New 90-inch Odor Control Header being rigged into place
     New odor control fans being shop tested to confirm operation
    Previous  1  of   Next    90-inch duct and dampers removed from odor control room
     Sawcutting walls in Grit Room for temporary duct work
     Temporary ductwork in Grit Room prior to replacing new ductwork
     Sluice gates at emergency spillway that will be replaced
     Portable operator to close spillway gates if power is lost.
    Previous  1  of   Next    Demolition of sodium hypochlorite containment wall
     Site of future sodium hydroxide (caustic) storage tanks and pumps
     Ductwork from grit area to feed odor control room
     Next month's work at emergency spillway stop logs and sluice gates
    Previous  1  of   Next    Odor Control Roof with removable covers for equipment access to wet scrubbers and CAD-1
     Temporary waterproofing at removable concrete planks on Odor Control Roof
     Ductwork and heat exchanger below removable roof planks that will be demolished in Odor Control Room
     Demolition of existing wet scrubber recirculation pumps
     Electrical conduits installed in the Odor Control Room to power new equipment
    Previous  1  of   Next    Contractor establishing work zone with concrete barriers, fences and screens at the Odor Control Roof
     Contractor removing soil from Odor Control Roof
     Location of new odor control fan that will replace the fan that was damaged in the 2016 fire
    Previous  1  of   Next