Update for Nut Island Headworks Odor Control and HVAC Improvements Project (Contract 7548)

Project type
Sewer
Project status
Address
Nut Island facility
Communities

About this Project

The Nut Island Headworks Odor Control and HVAC Systems Improvements project involves an extensive rehabilitation of the facility that will ensure that Nut Island continues to work as designed.  Odor Control facility access, fuel tank replacement and other appurtenances will be rehabilitated.  This project will take approximately 36 months to complete.In January 2020, this $187,410.85 contract was awarded to Walsh Construction.

The first phase of work will begin on Tuesday, April 21, 2020.  The work involves the installation of erosion controls (silt fencing and straw waddles), catch basin inlet protection, tree protection, temporary chain link fence and concrete barriers delineating work zones.  The initial work will be followed by establishing a temporary construction laydown area.  Once these activities are complete, the next phase of work will begin in May at the Nut Island facility.

Public Access Plan

Public Access paths will remain open during construction.  Please obey all posted signage on site.

Contact

If you have any questions please contact MWRA Public Affairs.

Updates

Sign up for electronic project notifications and updates through our Everbridge service.

July 11, 2023

7548 NIHW Odor Control HVAC Improvement Project
Perforated Pipe and Crushed Stone Trench Drain
7548 NIHW Odor Control HVAC Improvement Project
Roof waterproofing transition
7548 NIHW Odor Control HVAC Improvement Project
Carbon Adsorber (CAD) 2 Fiber Reinforced Plastic (FRP) 90 degree elbow
7548 NIHW Odor Control HVAC Improvement Project
Deluge Piping Connection
7548 NIHW Odor Control HVAC Improvement Project
Parking lot mill and overlay

June 13, 2023

7548 NIHW Odor Control HVAC Improvement Project
Loading Carbon into new Carbon Adsorber Unit (CAD) System
7548 NIHW Odor Control HVAC Improvement Project
CAD unit Interior view
7548 NIHW Odor Control HVAC Improvement Project
Odor Control Roof Panel Placement
7548 NIHW Odor Control HVAC Improvement Project
Odor Control Roof Surfacing
7548 NIHW Odor Control HVAC Improvement Project
Odor Control Roof Insulation
7548 NIHW Odor Control HVAC Improvement Project
Stair 12 near bench shaft
7548 NIHW Odor Control HVAC Improvement Project
Sidewalk Repair adjacent to Emergency Spillway

March 29, 2023

7548 NIHW Odor Control HVAC Improvement Project
Layout of all CAD (Carbon Adsorber) vessels
7548 NIHW Odor Control HVAC Improvement Project
Catwalk access to wet scrubbers and dampers
7548 NIHW Odor Control HVAC Improvement Project
Screening Room Odor Control Fiber Reinforced Plastic (FRP) Replacement
7548 NIHW Odor Control HVAC Improvement Project
Odor Control Roof Panels

March 2, 2023

7548 NIHW Odor Control HVAC Improvement Project
Fiber Reinforced Plastic (FRP) duct
7548 NIHW Odor Control HVAC Improvement Project
Carbon Adsorber Inlet and Outlet Ducts
7548 NIHW Odor Control HVAC Improvement Project
Carbon Adsorber Power and Controls
7548 NIHW Odor Control HVAC Improvement Project
Generator Room Air Handling Unit (AHU) replacement

February 2, 2023

7548 NIHW Odor Control HVAC Improvement Project
All carbon vessels delivered and being set in place
7548 NIHW Odor Control HVAC Improvement Project
CAD #9 & 10 Inlet and Outlet ducts
7548 NIHW Odor Control HVAC Improvement Project
CAD #1 and 2 topping slab
7548 NIHW Odor Control HVAC Improvement Project
Odor control roofing to resume in the spring
7548 NIHW Odor Control HVAC Improvement Project
FRP Duct and grease filters in grit room

December 28, 2022

7548 NIHW Odor Control HVAC Improvement Project
View of control room
7548 NIHW Odor Control HVAC Improvement Project
Rigging first CAD vessel
7548 NIHW Odor Control HVAC Improvement Project
CAD foundations and topping slab
7548 NIHW Odor Control HVAC Improvement Project
Stack Expansion Joints
7548 NIHW Odor Control HVAC Improvement Project
Odor Control Roofing

November 7, 2022

7548 NIHW Odor Control HVAC Improvement Project
CAD area topping slab demolition to build new foundation
7548 NIHW Odor Control HVAC Improvement Project
CAD foundations
7548 NIHW Odor Control HVAC Improvement Project
CAD vessels 9 & 10
7548 NIHW Odor Control HVAC Improvement Project
FRP Duct replacement

August 9, 2022

7548 NIHW Odor Control HVAC Improvement Project
Masonry work has begun on Stair 12 super structure
7548 NIHW Odor Control HVAC Improvement Project
The wet scrubber testing (pH & ORP probes)
7548 NIHW Odor Control HVAC Improvement Project
Supply air duct in Odor Control Room
7548 NIHW Odor Control HVAC Improvement Project
Odor Control roof with temporary removable panels over carbon adsorbers
7548 NIHW Odor Control HVAC Improvement Project
Hot water piping in screen room in AHU-5 & 6

June 29, 2022

7548 NIHW Odor Control HVAC Improvement Project
7548 NIHW Odor Control HVAC Improvement Project
Constructing stair 12 Masonry and tie into existing bench structure

April 28, 2022

7548 NIHW Odor Control HVAC Improvement Project
Odor Control Stainless FRP Duct
7548 NIHW Odor Control HVAC Improvement Project
dor Control FRP Duct Installation
7548 NIHW Odor Control HVAC Improvement Project
Wet Scrubber Rehab and Chemical Pumps
7548 NIHW Odor Control HVAC Improvement Project
Odor Control Fan #2 (fan and damper controls)
7548 NIHW Odor Control HVAC Improvement Project
AHU-3 & 4 rigging (Truck Bay hatch hoist)

March 31, 2022

7548 NIHW Odor Control HVAC Improvement Project
Odor Control Stainless Steel Duct Installation
7548 NIHW Odor Control HVAC Improvement Project
Odor Control FRP Duct Installation
7548 NIHW Odor Control HVAC Improvement Project
Wet Scrubber Rehab (Chevron Mist Eliminators, spray nozzles and media)
7548 NIHW Odor Control HVAC Improvement Project
Odor Control Fan #2
7548 NIHW Odor Control HVAC Improvement Project
Stair 12 at ground level. Masons will begin building a stair tower.
7548 NIHW Odor Control HVAC Improvement Project
Air Handler Replacement (AHU- 1 & 2) will serve pump and blower room

March 3, 2022

7548 NIHW Odor Control HVAC Improvement Project
Odor Control Duct Installation at Wet Scrubbers
7548 NIHW Odor Control HVAC Improvement Project
Chemical Feed System
7548 NIHW Odor Control HVAC Improvement Project
Air Handler Replacement (Pump & Blower Room)

February 3, 2022

7548 NIHW Odor Control HVAC Improvement Project
Odor control fan #1 and 2 pads
7548 NIHW Odor Control HVAC Improvement Project
Wet scrubber & 90-inch Duct Demo
7548 NIHW Odor Control HVAC Improvement Project
Elevated walkway platform (access to dampers and controls)
7548 NIHW Odor Control HVAC Improvement Project
8-inch Sanitary Ejector Piping

January 5, 2022

7548 NIHW Odor Control HVAC Improvement Project - 001
New fuel oil tanks in service
7548 NIHW Odor Control HVAC Improvement Project
Temporary heating coil
7548 NIHW Odor Control HVAC Improvement Project - 003
Odor control fans
7548 NIHW Odor Control HVAC Improvement Project
Odor Control Fan Headers (new fan on left, old fan on right)
7548 NIHW Odor Control HVAC Improvement Project
Caustic storage tanks and pumps

November 3, 2021

7548 NIHW Odor Control HVAC Improvement Project
Utility relocation at Stair 12 (Building code requires new egress path)
7548 NIHW Odor Control HVAC Improvement Project
HVAC duct replacement in Grit Area
7548 NIHW Odor Control HVAC Improvement Project
Underground fuel oil tank piping and wiring
7548 NIHW Odor Control HVAC Improvement Project
Breeching for new boilers

September 28, 2021

7548 NIHW Odor Control HVAC Improvement Project
Setting one of the 20,000 Fuel Oil Storage Tanks
7548 NIHW Odor Control HVAC Improvement Project
20,000 Gallon Underground Fuel Oil Storage Tanks in place
7548 NIHW Odor Control HVAC Improvement Project
Odor control duct being rigged into the odor control room
7548 NIHW Odor Control HVAC Improvement Project
Wet Scrubber #3 Inlet Duct fitup
7548 NIHW Odor Control HVAC Improvement Project
Carbon absorber #1 demolition

September 7, 2021

7548 NIHW Odor Control HVAC Improvement Project
Temporary OC Duct (preliminary testing to test flow for changes)
7548 NIHW Odor Control HVAC Improvement Project
Temporary Supply Air Fans
7548 NIHW Odor Control HVAC Improvement Project
Emergency slide gate 3
7548 NIHW Odor Control HVAC Improvement Project
Excavation for new underground storage tanks

August 6, 2021

7548 NIHW Odor Control HVAC Improvement Project
OC #4
7548 NIHW Odor Control HVAC Improvement Project
Portable CAD Unit (ductwork outside)
7548 NIHW Odor Control HVAC Improvement Project
Caustic Feed System
7548 NIHW Odor Control HVAC Improvement Project
Boiler Replacement

April 27, 2021

7548 NIHW Odor Control HVAC Improvement Project
Fan 4 intake (suction) prior to installation of additional Odor Control Duct
7548 NIHW Odor Control HVAC Improvement Project
Spare fan wheel
7548 NIHW Odor Control HVAC Improvement Project
Exhaust from fan 4 as it enters the header
7548 NIHW Odor Control HVAC Improvement Project
Odor control room (future hypochlorite location)
7548 NIHW Odor Control HVAC Improvement Project
Sub-contractor prep work to get fan up and running
7548 NIHW Odor Control HVAC Improvement Project
New stainless steel ducts in grit level
7548 NIHW Odor Control HVAC Improvement Project
Stop log guide rail

March 31, 2021

7548 NIHW Odor Control HVAC Improvement Project
Odor Control Fan #4 set in place & grouting base frame
7548 NIHW Odor Control HVAC Improvement Project
New Odor Control SCADA cabinet set in pump and blower room
7548 NIHW Odor Control HVAC Improvement Project
New caustic tanks set in place
7548 NIHW Odor Control HVAC Improvement Project
Chemical fill piping for sodium hypochlorite and sodium hydroxide
7548 NIHW Odor Control HVAC Improvement Project
Temporary carbon absorber unit
7548 NIHW Odor Control HVAC Improvement Project
HVAC duct work in screen room
7548 NIHW Odor Control HVAC Improvement Project
Work at spillway, finishing grouting rails and planning stop logs

March 2, 2021

7548 NIHW Odor Control HVAC Improvement Project
Stop log frames being installed in the emergency spillway. There is a yellow crane hauling some logs.
7548 NIHW Odor Control HVAC Improvement Project
Stop log frames being installed in the emergency spillway. Workers installing structures at spillway.
7548 NIHW Odor Control HVAC Improvement Project
90-inch odor control fan header installed
7548 NIHW Odor Control HVAC Improvement Project
Forms for new odor control dan foundation
7548 NIHW Odor Control HVAC Improvement Project
Caustic storage tanks delivered and stored on site

February 3, 2021

7548 NIHW Odor Control HVAC Improvement Project
Temporary Ductwork at grit level
7548 NIHW Odor Control HVAC Improvement Project
Temporary duct system to provide ventilation while existing ductwork gets replaced
7548 NIHW Odor Control HVAC Improvement Project
Temporary fans to provide ventilation while air handlers get replaced
7548 NIHW Odor Control HVAC Improvement Project
Outdoor roof and removable covers and ductwork being delivered to site
7548 NIHW Odor Control HVAC Improvement Project
New 90-inch Odor Control Header being rigged into place
7548 NIHW Odor Control HVAC Improvement Project
New odor control fans being shop tested to confirm operation

December 14, 2020

7548 NIHW Odor Control HVAC Improvement Project
90-inch duct and dampers removed from odor control room
7548 NIHW Odor Control HVAC Improvement Project
Sawcutting walls in Grit Room for temporary duct work
7548 NIHW Odor Control HVAC Improvement Project
Temporary ductwork in Grit Room prior to replacing new ductwork
7548 NIHW Odor Control HVAC Improvement Project
Sluice gates at emergency spillway that will be replaced
7548 NIHW Odor Control HVAC Improvement Project
Portable operator to close spillway gates if power is lost.

October 29, 2020

7548 NIHW Odor Control HVAC Improvement Project
Demolition of sodium hypochlorite containment wall
7548 NIHW Odor Control HVAC Improvement Project
Site of future sodium hydroxide (caustic) storage tanks and pumps
7548 NIHW Odor Control HVAC Improvement Project
Ductwork from grit area to feed odor control room
7548 NIHW Odor Control HVAC Improvement Project
Next month's work at emergency spillway stop logs and sluice gates

October 2, 2020

7548 NIHW Odor Control HVAC Improvement Project
Odor Control Roof with removable covers for equipment access to wet scrubbers and CAD-1
7548 NIHW Odor Control HVAC Improvement Project
Temporary waterproofing at removable concrete planks on Odor Control Roof
7548 NIHW Odor Control HVAC Improvement Project
Ductwork and heat exchanger below removable roof planks that will be demolished in Odor Control Room
7548 NIHW Odor Control HVAC Improvement Project
Demolition of existing wet scrubber recirculation pumps
7548 NIHW Odor Control HVAC Improvement Project
Electrical conduits installed in the Odor Control Room to power new equipment

June 16, 2020

7548 NIHW Odor Control HVAC Improvement Project
Contractor establishing work zone with concrete barriers, fences and screens at the Odor Control Roof
7548 NIHW Odor Control HVAC Improvement Project
Contractor removing soil from Odor Control Roof
7548 NIHW Odor Control HVAC Improvement Project
Location of new odor control fan that will replace the fan that was damaged in the 2016 fire