MWRA's Metropolitan Water Tunnel Program (MWTP) will add redundancy for MWRA's existing Metropolitan Tunnel System. Redundancy will provide multiple routes for more reliable water delivery to Metro Boston, and allow our aging, existing water tunnel system to be rehabilitated without interrupting service. MWRA and its contractors will perform work in seven communities where the two MWTP tunnels are planned to be constructed: Boston, Brookline, Needham, Newton Waltham, Wellesley and Weston. This work may be seen along city streets and can have impacts on neighborhoods. MWRA’s Community Relations Department works with municipal staff and residents to ensure good communications during these projects.

Meetings in Newton

  • Informaton about public meetings in your town will be posted here.

Geotechnical Work in Newton

The Metropolitan Water Tunnel Program is working on the geotechnical investigation at specific locations in your community.  The following fact sheet explains geotechnical investigation work.

Notices for Abutters in Newton

Notices are distributed to those abutting work to notify them of work in their area.

Active Notices

There are no active notices at this time.

Archive

January, 2024

01/08/2024: Field work on the DCR Leo J Martin Memorial Golf Course property in Newton

September, 2023

09/12/2023: Field work within the City of Newton easement at the end of Nickerson Road near the intersection of Drew Road

August, 2023

08/10/2023: Field work within the City of Newton’s Hartmann Park

July, 2023

07/24/2023: Field work at the northern corner of the intersection of Christina Street and Goddard Street, on land owned by the City of Newton

07/06/2023:Field work in Newton Lower Falls, Hamilton field area

June, 2023

06/20/2023: Field work within the City of Newton’s Hartmann Park, limited to one area along the side near Country Club Road

August, 2022

08/11/2022: Field work at Countryside Road, within the former water tower parcel

08/03/2022: Field work at Quinobequin Road
between the intersections with Grove Street and Washington Street (Rt. 16)

May, 2022

05/20/2022: Field work at Leo J. Martin Memorial Golf Course near the 16th hole and Pine Grove Avenue

April, 2022

04/28/2022: Field work at wooded area along the former railroad grade at the edge of the Leo J. Martin Golf Course, and along the sidewalk on Pierrepont Road

04/28/2022: Field work along the south side of Dedham Street

04/28/2022: Field work in Baldpate Hill Road area

June, 2021

06/16/2021: Field work near 177 Brandeis Road, across the street from Newton South High School and south of the tennis courts

April, 2021

04/29/2021: Field work at West Pine Street, Auburndale Park, Pine Grove Avenue, Hamilton Park and Quinobequin Road

Contact Us

Please contact Carmine DeMaria, MWRA Community Relations Coordinator, or Tunnels.Info@mwra.com if you have any questions or concerns about the Metropolitan Water Tunnel Program.