|
Combined Sewer Overflows
Massachusetts Water Resources Authority
Not all sewer systems
are created equal. While modern systems transport rainwater and
sewage from homes and businesses through separate pipes, some older systems
like Boston's have "combined" sewers that carry both flows together. During
normal conditions flows are delivered to treatment plants.
During very heavy rains, when flows sometimes double and even triple, these
systems become overloaded. Built-in overflows (called combined sewer overflows
or "CSOs") must then act as relief points by releasing excess flows into the nearest body
of water. This prevents sewage backups into homes and onto area streets,
but it does so at considerable cost to local water quality.
WHERE CSOs ARE LOCATED
Boston, Cambridge, Chelsea and Somerville have combined sewer systems
that connect to MWRA's system. In 1987, a total of 84 active, uncontrolled CSOs discharged combined flows into Boston Harbor and into the Charles, Mystic Neponset Rivers.
WHY CSOs MUST BE CONTROLLED
CSOs occasionally discharge a combination of rainwater and sewage into Boston Harbor, the Charles, the Mystic and the Neponset Rivers.
WHAT IS BEING DONE ABOUT CSOs?
As of December 31, 2007:
|
- 24 of the 84 original CSOs
have been closed.
- Annual CSO volumes have been reduced by 81% overall.
|
CSO CONTROL PLAN
Since MWRA was created in 1985, solving the problems related to CSOs has
been a top priority. MWRA developed a CSO Control Plan in 1994. The plan has since undergone environmental review
and received federal and state approvals, allowing the projects to move
forward on a design and construction schedule mandated by the Federal
Court as part of the Boston Harbor Case.
The CSO Control Plan been revised over time to reduce cost and to make best use of improving
technology.
As of December 31, 2007: |
- 21 of the 35 original CSO Control Plan projects have been completed.
|
Back to top
HOW CSO FACILITIES WORK
MWRA operates facilities that screen and chlorinate combined wastewater (sewage and storm water) prior to discharge or further treatment.
MWRA's CSO facilities at Union Park (Boston), Cottage Farm and Prison Point (Cambridge) store and pump CSO flows. Screened and chlorinated wastewater can be stored and pumped back into the system for processing at at the Deer Island treatment plant. Any treated wastewater that exceeds a facility's storage capacity is be discharged through CSO outfalls.
At the Somerville Marginal facility, combined wastewater flows enter and leave the facility by gravity, not pumping. The wastewater is screened, chlorinated and dechlorinated. The disinfected wastewater overflows into its receiving water as quickly as it arrives at the facility.
Back to top
RECENTLY COMPLETED CSO CONTROL PROJECTS (2006-2007) |
Total volume of CSO discharges reduced by 226.7 Million Gallons |
STONY BROOK SEWER SEPARATION (CHARLES RIVER) |
|
Removed stormwater runoff from neighborhood and MWRA sewers by installing 74,000 feet of new storm drains serving 609 acres in Jamaica Plain, Mission Hill and Roxbury. Completed: Sept. 2006. Cost: $45,056,000. |
Total Reduction of CSO Volume: 99.7% |
Frequency of discharges |
| Before project |
22 times per year |
| After project |
2 times per year |
Volume of discharges |
| Before project |
44.5 million gallons/year |
| After project |
0.13 million gallons/year |
SOUTH DORCHESTER BAY SEWER SEPARATION |
|
Removed stormwater runoff from neighborhood and MWRA sewers by installing 136,000 feet (over 25 miles) of new storm drains serving 1,750 acres of Dorchester from Dorchester Bay to Washington St. and from Columbia Rd. to as far south as the Neponset River. Completed: Dec., 2006. Cost: $118,229,000. |
Total Reduction of CSO Volume: 100%
|
Frequency of discharges |
| Before project |
20 times per year |
| After project |
All discharges eliminated |
Volume of discharges |
| Before project |
30 million gallons/year |
| After project |
All discharges eliminated |
FORT POINT CHANNEL SEWER SEPARATION |
|
Removed stormwater runoff from neighborhood and MWRA sewers by installing 4,550 feet of new storm drains serving 55 acres in the Fort Point Channel area. Completed: March 2007. Cost: $7,675,000. |
Total Reduction of CSO Volume: 100% |
Frequency of discharges |
| Before project |
9 times per year |
| After project |
0 times per year |
Volume of discharges |
| Before project |
3.0 million gallons/year |
| After project |
0.0 gallons/year |
PRISON POINT FACILITY OPTIMIZATION |
|
Minimizes treated CSO discharges to the Inner Harbor by optimizing the operation of existing facility gates and pumps to maximize in-system storage and convey more flow to Deer Island. Completed: March, 2007. Cost: $50,000. |
Total Reduction of CSO Volume: 25.4% |
Frequency of discharges |
| Before project |
30 times per year |
| After project |
17 times per year |
Volume of discharges |
| Before project |
335 million gallons/year (treated) |
| After project |
250 million gallons/year (treated) |
BOS019 CSO STORAGE CONDUIT- (LITTLE MYSTIC CHANNEL) |
|
Construction of new facility to provide 670,000 gallons of off-line storage in double barrel 10’x17’ conduits installed between Chelsea St. and the Mystic Tobin Bridge, Charlestown. Completed: March 2007. Cost: $14,283,000 |
Total Reduction of CSO Volume: 86.4% |
Frequency of discharges |
| Before project |
13 times per year |
| After project |
2 times per year |
Volume of discharges |
| Before project |
4.4 million gallons/year |
| After project |
0.6 million gallons/year |
UNION PARK DETENTION/TREATMENT FACILITY - (FORT POINT CHANNEL) |
|
Construction of new facility, adjacent to existing BWSC pump station, to provide 2.2 million gallons of storage, and treatment of remaining discharges. Completed: April, 2007. Cost: $49,546,000. |
Total Reduction of CSO Volume: 45.9%
(100% treated) |
Frequency of discharges |
| Before project |
25 times per year (untreated) |
| After project |
17 times per year (treated) |
Volume of discharges |
| Before project |
132.0 million gallons/year (untreated) |
| After project |
71.4 million gallons/year (treated) |
Back to top
IS MWRA CLEANING UP THE CHARLES RIVER?
The MWRA has already achieved significant reduction of CSO related impacts to the Charles River. Wastewater system improvements already completed have dramatically reduced combined sewer overflows to the Charles River by transporting much more flow to MWRAs new Deer Island Treatment Plant. Also, the MWRAs Cottage Farm CSO facility on the Charles River at the BU Bridge has been upgraded to optimize treatment system performance and minimize potential harm to aquatic life in the river posed by discharges.
Evidence of a cleaner Charles River is emerging:
- The river is now generally safe for recreational boating.
- Dry weather bacteria counts have been decreasing. In 1998, 90% of water quality samples taken by MWRA met the boating standard.
- Healthy populations of river herring in the Charles provide the Division of Marine Fisheries with fish to stock other Massachusetts Rivers.
Besides implementing CSO control projects and conducting its own water quality investigations of the Charles River, MWRA has provided financial support to the Charles River Watershed Associations studies, and is also an active participant in the U.S. Geological Surveys Lower Charles River Project.
Back to top
WHAT
WILL THE PLAN COST?
In 1990, MWRA and its engineering consultants recommended a $1.3 billion
dollar CSO plan that called for an extensive system of pipes that would
drop wet-weather flows into deep, bedrock tunnels where they would be
stored temporarily until being pumped to Deer Island for treatment. In
1994, a second look at both CSOs and the entire sewer system brought a
different solution. The new plan, with a price tag of approximately $650
million, is in keeping with new state and federal CSO policies and takes
into account other MWRA facility improvements that also reduce CSO volumes
and impacts. This plan recognizes that sewer system improvements have
already reduced CSO volumes significantly and provided treatment for the
majority of the remaining flows.
Back to top
CSO PROJECTS BY COMMUNITY
Boston
- Fox Point CSO Facility
Upgrade
- Commercial Point
CSO Facility Upgrade
- Neponset Sewer Separation
- Constitution Beach
Sewer Separation
- East Boston Branch
Relief Sewer
- Union
Park Detention/Treatment Facility
- North
Dorchester/Reserved Channel Conduits and Treatment
- Fort
Point Channel CSO Storage
- South
Dorchester Bay Sewer Separation
- Stony
Brook Sewer Separation
- Floatables Control
- Localized hydraulics
relief project
Cambridge
Somerville
- Somerville Marginal
CSO Facility Upgrade
- Localized sewer
separation projects
- Floatables Control
Chelsea
- City of Chelsea
Trunk Sewer Relief
- MWRA Chelsea Branch
Sewer Relief
- Chelsea Outfall
Rehabilitation
- Floatables Control
Back to top
Rev.
13-Aug-2008 5:27 PM
|