Return to mwra.com home

Massachusetts Water Resources Authority
PROJECT UPDATE

Date:

Updated April 2, 2024

Contact:

Troy Wall
(617) 305-5762, Troy.Wall@mwra.com


Section 89 Northern Intermediate High Pipeline Replacement
(MWRA Contract 7117)


image of pump station

About this Project:

MWRA’s Northern Intermediate High (NIH) pressure zone has supplied water to the communities of Reading, Stoneham, Wakefield, Wilmington, Winchester, and Woburn through a single 48-inch diameter pipeline, fed by the Gillis and Spot Pond Pumping Stations in Stoneham.  MWRA recently completed the NIH Redundancy Project with the installation and activation of the new Section 110 pipeline through the communities of Stoneham, Reading and Woburn.  Section 110 provides full pipeline redundancy for the water supply to the NIH communities. Activation of the new Section 110 pipeline has allowed MWRA to proceed with design and construction for the replacement of Section 89, which has previously been the single transmission line to the NIH communities.  Section 89 was installed in the 1970’s and is made of material called pre-stressed concrete cylinder pipe (PCCP), which has been susceptible to catastrophic failure.  With the new redundant water pipeline in place, MWRA will be able to proceed with the replacement of the vulnerable PCCP portions of Section 89 with the new ductile iron pipe. This $32.6 million contract was awarded to P.Gioioso & Sons, Inc. in May 2021 for a contract term of 1475 calendar days from the Notice to Proceed.

Summary Scope of New Work:

Section 89 of the Northern Intermediate High Pipeline is being replaced for added water distribution and redundancy in the Town of Winchester, Woburn, Stoneham and the Town of Wakefield.

  • Removal of approximately 10,500 linear feet of 48-inch diameter PCCP water main
  • Installation of new 48-inch steel and ductile iron water main and appurtenances in Stoneham, Winchester, and Woburn by open­cut methods.
  • Furnish and install new 48-inch valves, precast valve vaults, air valves, blow-off assemblies, manholes and all appurtenant work along the 10,500 linear feet.
  • Removal and replacement of valves, precast valve vaults, air valves, blow- off assemblies, manholes along 9,000 linear feet of 36-inch diameter ductile iron water main, in Woburn.
  • Installation of linestops and bypass piping to facilitate isolation at the Bear Hill Tank connection.
  • Abandonment of approximately 6,000 linear feet of 24-inch diameter water main, Section 29, in Stoneham.
  • Transfer of service and meter connections from Section 29 to Section 110. Replacement of Meter 200 due to age and condition of interior piping and fittings within the existing meter vault on Washington Street.
  • Removal, handling, transportation and disposal of rock, contaminated soil and groundwater along the pipeline routes.
  • Restoration of all disturbed areas and utilities impacted by the work.

    For more information, please contact MWRA Public Affairs.

Updates

April 2, 2024

Project Overview:

  • Crew has commenced work on Fallon Road in Stoneham
  • Wetland Restoration, tree planting and paving on Montvale Avenue and Washington Street in Woburn will be completed in Spring 2024

Fallon Road Stoneham – Bear Hill Tank
To maintain Flow to Bear Hill Tank during construction, it was necessary to install 760 linear feet of 18-inch, 24-inch and 30-inch ductile iron & high density polyethylene piping with isolation valves to maintain flow to Bear Hill Tank and flow to the surrounding communities.

Sign up for electronic project notifications and updates through our Everbridge service.


Bypass piping along Fallon Road in Stoneham, connecting to the 16-inch Stoneham line

End of Fallon Road, two 18-inch lines

Line Stop being installed

March 21, 2023 -

MWRA Construction May Cause Possible Reduced Water Pressure, Discolored Water in Stoneham/Wakefield/ Reading/Winchester/Woburn

  • Beginning Monday, March 25, 2024, MWRA has arranged with the Towns of Reading, Stoneham, Wakefield, Wilmington, and Winchester, and the City of Woburn to schedule a temporary shutdown and bypassing of a critical water supply line near Fallon Road in Stoneham.
    • This shutdown is necessary to replace the aging pipe infrastructure, and prevent the risk of an uncontrolled break and loss of service.
    • This work will ensure a more reliable water system is in place for residents and businesses to benefit from.
  • The work on Monday is expected to take upwards of 4 to 5 days to complete, working continuously for 24 hours each day; during this time water users may expect lower pressure in Reading, Stoneham, Wakefield, Woburn, and the area of Bellevue Avenue/Eugene Drive in Winchester.
    • Normal water pressure is expected to be restored by Friday, March 29, 2024.
  • Discolored water may also be possible for 1 to 2 days following the redirection of water flow for this work. If discolored water does occur, it will be from a small amount of iron in local pipes.
    • Please note that iron will stain light colored items in your laundry, especially when bleach is used. Residents should check water clarity before washing any white or lighter colored laundry during this period of work. Residents may want to wait for the water to clear before using it.

If you have any questions or concerns, please contact MWRA Community Relations Liaison, Troy Wall at (617) 305-5762 or Troy.Wall@mwra.com.

.Sign up for electronic project notifications and updates through our Everbridge service.

February 13, 2024

Project Overview:

  • Project is 60% complete
  • Washington Street & Montvale Avenue permit for work to be done at night

Sign up for electronic project notifications and updates through our Everbridge service.

Setting GV Structure at Utica night work

Setting GV Structure

Section 89 Chlorination


Fallon Road Stoneham – Bear Hill Tank
760 linear feet of 18’, 24’ and 30” of Ductile Iron & High density polyethylene piping with isolation valves to maintain flow to Bear Hill Tank

Deliveries to Fallon Road

December 4, 2023 -Construction Update

  • The MWRA’s contractor, P. Gioioso & Sons of Hyde Park, MA, is currently working at night (7:00PM to 5:00AM) along Montvale Avenue and Washington Street in the City of Woburn.
  • Currently, night work is in the final stages and is expected to be completed before the Chirstmas holiday.
  • Once this work has been completed, the contractor will demobilize all the equipment and materials currently located on Albany Street, and the MWRA will activate the new pipeline.
  • Final overlay paving of Albany Street, Montvale Avenue, and Washington Street is scheduled for a later date in 2024.

.Sign up for electronic project notifications and updates through our Everbridge service.

December 4, 2023

Sign up for electronic project notifications and updates through our Everbridge service.

  • Contractor continues to install new 36-inch water main on Washington Street during night. Expected completion of this work is this December after which they will demobilize.
  • Following installation MWRA will pressure test, chlorinate, and activate  new pipeline.
  • Contractor will mobilize to Fallon Road Stoneham in January 2024

Montvale Avenue night work (light towers located at different locations for visibility)

Montvale Avenue night work (light towers located at different locations for visibility)

Washington Street night work

Washington Street night work

October 10, 2023

Sign up for electronic project notifications and updates through our Everbridge service.

Washington Street-local water and sewer

Washington Street-local water and sewer

Washington Street-local water and sewer

Washington Street-local water and sewer

Albany Street & Montvale Avenue at Night-installation of 36-inch ductile iron pipe

August 3, 2023

Sign up for electronic project notifications and updates through our Everbridge service.

  • The MWRA and its contractor, P. Gioioso & Sons of Hyde Park, MA, will be working along Washington Street between Montvale Avenue and Utica Street and along Montvale Avenue between Albany Street and Washington Street at night from 7:00PM to 5:00AM. Work will be conducted Monday through Thursday (into Friday morning) starting on Monday, August 14, 2023.
  • This first phase involves replacement of the City water lines and sewers on Washington Street to create a corridor for the new 48-inch MWRA water pipeline.
  • Once the City water and sewers are relocated, the second phase will move to Montvale Ave to begin removing the existing MWRA water pipeline and installing a new 48 inch water pipeline under the roadway.
  • Work is expected to last approximately two to three months.
  • In order to safely conduct the work, this section of Washinton Street will have limited access to through traffic; and two vehicular lanes will be closed to traffic along Montvale Avenue (one lane in each direction will be open).
  • Importantly, access to businesses or residences will remain available during overnight construction hours.
  • Furthermore, traffic patterns will be clearly marked, and police details will be on site to assist with the flow of traffic.
  • During non-work hours, Washington Street and Montvale Avenue will not have any traffic restrictions.

The new 48-inch ductile iron water main recently installed along albany Street in the City of Woburn, which is part of this project.

July 11, 2023

Sign up for electronic project notifications and updates through our Everbridge service.

  • Contractor installed 1450 linear feet of 48-inch pipe
  • Eversource completed work
  • Starting mid-July Montvale Avenue at night
  • Woburn permit states Washington Street work hours are nights

Albany Street in Woburn

Albany Street in Woburn

June 13, 2023

Sign up for electronic project notifications and updates through our Everbridge service.

Easement – replace existing 48-inch Pre-stressed Concrete Cylinder Pipe (PCCP) with new 48-inch Ductile Iron Pipe

Easement - Winchester to Woburn

Albany Street Woburn

March 29, 2023

Sign up for electronic project notifications and updates through our Everbridge service.

Crew No 1 – Installation of 24 inch pipe to Meter 234 complete (Disinfection, Sampling and Activation)

Crew 2 at Aberjona River - Access pits on both sides and install of new 36 inch pipe inside existing 48 inch pipe

Completed Section 29 Stoneham - abandonment disconnecting all existing valves at zoo and Stoneham and filling pipeline with flow fill

Easement – Replace existing 48 inch PCCP with ductile

March 2, 2023

Sign up for electronic project notifications and updates through our Everbridge service.

Installation of new valve vault structure on Forest Street

Steel Sheeting for sliplining pits

Access pits on both sides-installation of new 36-inch pipe inside existing 48-inch pipe

Crew No 3-Section 29 of Abandonment consists of disconnecting all existing valves at Zoo and Stoneham and filing pipeline with flowfill

February 2, 2023

Sign up for electronic project notifications and updates through our Everbridge service.

Installation of new MWRA gate valve and Gillis Pump Station interconnection

Forest Street Bypass in Winchester

December 28, 2022

Sign up for electronic project notifications and updates through our Everbridge service.

Installation of new MWRA gate valve and Gillis Pump Station interconnection

Blow off Washington Street

Washington Street Gate Valve

November 7, 2022

Sign up for electronic project notifications and updates through our Everbridge service.

Installation of new MWRA supplied valve at straw point park

New supply line to the Stone Zoo

DCR pool area-replacing Section 29 20-inch cast iron pipe with new ductile iron

August 9, 2022

Sign up for electronic project notifications and updates through our Everbridge service.

Installation of large concrete valve structure on Fellsway

Installing new 48" ductile iron pipe

Forest Street in Winchester- completed installation of local 12” water main and new services

June 29, 2022

Sign up for electronic project notifications and updates through our Everbridge service.

Installation of 160 lf of 36’ DI pipe at Gillis Pump Station

Connection to Section 110

Forest Street in Winchester-installation of local 12” water main as well as installation of Meter 234 bypass water line


Test pits on Fallon Road to confirm material of pipe to Bear Hill tank. 

April 28, 2022

Sign up for electronic project notifications and updates through our Everbridge service.

Work Update:

  • Preconstruction surveys & photos
  • Meetings with DCR and MassDOT
  • Tree removal
  • Test pits to confirm OD of PCCP pipe
  • Installation of 24" pipe on South Street

Traffic message boards for upcoming work on Forest Street in Winchester

Section 89A:  36” PCCP - Fallon Road

March 31, 2022

Sign up for electronic project notifications and updates through our Everbridge service.

Section 89A:  36” T & S South Street

Section 89A:  36” PCCP - Fallon Road

February 3, 2022

Sign up for electronic project notifications and updates through our Everbridge service.

Work Update:

  • Submittals
  • Permits
  • Preconstruction surveys
  • Meetings with DCR and MassDOT
  • Tree protection/removal

Outside picture test pits, tree protection and signs

Test pits on Route 93 & Fallon Road

January 19, 2022

We will post project updates in this section.

Sign up for electronic project notifications and updates through our Everbridge service.

For more information, please contact MWRA Public Affairs.

Back to top



Follow us

twitter icon
flickr
YouTube button
Sign Up for Everbridge Notifications from MWRA