Return to mwra.com home
Massachusetts Water Resources Authority
PROJECT UPDATE

Date:

Updated September 7, 2021

Contact:

Jeffrey McLaughlin
617-305-5762, Jeffrey.McLaughlin@mwra.com


Weston Aqueduct Supply Main Rehabilitation - Medford, Somerville, Arlington
(Contract 6544)

image of pump station

image of pump station

About this Project:

MWRA’s Weston Aqueduct Supply Main 3 consists of approximately 10 miles of steel pipe installed in the 1920s and 30s. The pipe is a critical supply to over 250,000 customers in the Northern High, Northern Extra High and Intermediate High supply systems serving Waltham, Watertown, Belmont, Lexington, Bedford, Arlington, Somerville and Medford.  It also can provide emergency supply to the Gillis Pump Station serving communities of the North Shore and Northern Intermediate High communities. Figure 1 shows the full extent of the WASM 3 pipeline and the work limits for the current construction contract.

This first construction contract includes rehabilitation of approximately 13,800 feet of 56-inch and 60-inch diameter water main starting in Medford in December 2020, and continuing in Somerville and Arlington from Fall of 2021 to Spring of 2024. The rehabilitation will consist of cleaning and internal cement mortar lining of the pipe and adding valves for better operational flexibility.  Figure 2 shows the segments to be completed under this contract.

The work is restricted to low water demand months from September 15 to May 15, which necessitates three construction phases during the duration of the contract. This work restriction is necessary to ensure the main is operational during high summer demand periods. MWRA has awarded the construction contract to Albanese D&S of Dracut, MA.

Project Updates:

September 7, 2021

Upcoming Items:

  • Coordination with Somerville Housing Authority - access during construction and new building
  • Coordination with Arlington - Broadway Plaza businesses (making banners)
  • Removing some trees in Somerville
  • MWRA Ops - Reviewing Dewatering Plan for next segment

Test Pit at Meter 171 - Broadway and Palmer

August 6, 2021

Upcoming Items:

  • Coordination with Somerville Housing Authority
  • Coordination with Arlington
  • Removing some trees in Somerville

Map divided in 3 sections over th next 3 years
1. Ist section in Medfird complete
2. Arlington & Somerville setion next

WASM Activation in May - Testing for PH and Chlorine

Restoration of the ball field (water cannons and continuous rain has helped with restoration)

Restoration of ball field

April 27, 2021

Boston Avenue air valve structure

Dewatering blow off connection

Installation of new steel pipe

Restoration of ball field

March 31, 2021

Work Done To Date:

  • Complete access pits with new steel pipe
  • Restoration of construction areas
  • Disposal of contaminated soil off site
  • WASM3 planning for disinfection/activation

Recent completion of cement lining

Recent completion of cement lining

Cutting existing steel pipe

Arrival of new steel pipe

Installation of new steel pipe

Closure of access pits

March 2, 2021

Cutting 60-inch steel water main in preparation or forthcoming replacement section

Mixing and conveying cement for rehabilitation of the water pipe

Machinery utilized for applying cement lining during rehabilitation of the pipeline

Steam machine for concrete curing

February 3, 2021

Work Done To Date:

  • Rehab of WASM 3 – Work will be conducted from Sept 15 to May 15th due to demand
  • Cleaning and cement mortar lining of approximately 4,870 feet of 56-inch steel water main
  • Cleaning and cement mortar lining of approximately 8,310 feet of 60-inch steel water main
  • Furnishing and installing (4) butterfly valves and appurtenances.

WASM 3 - recent work: Installing Access Pits

WASM 3 - recent work: Installing Access Pits

Removing section of pipe - tuberculation

Removing section of pipe - tuberculation

Cleaning

Rivets connecting pipes

November 25, 2020

Construction Update

Contruction updates will be posted here.

Sign up for electronic project notifications and updates through our Everbridge service.


Follow us
twitter icon
flickr
YouTube button

Back to top

Updated: September 10, 2021
Original Post: November 25, 2020