PROJECT UPDATE

Updated:

First Post:

September 20, 2017

September 12, 2017

Contact:

Jeff McLaughlin
(617) 305-5762, Jeffrey.McLaughlin@mwra.com


Update for Sections 23, 24 and 47 Water Rehabilitation
in Boston, Newton and Watertown (MWRA Contract 6385)

map of project area

Go to Project Updates

About this Project:

This project is in design. Planned work includes the rehabilitation of MWRA water main sections 23, 24 and 47. The project will improve the condition of the existing water mains' hydraulic capacity and reliability and improve redundancy in the Southern High water service area. It will also facilitate water service from Shaft 7 of the City Tunnel to the MWRA Southern High Service communities of Boston, Newton and Watertown.

For more information, please contact Jeff McLaughlin at (617) 305-5762, or by email at Jeffrey.McLaughlin@mwra.com.

Project Updates

09/20/2017 Update

Boring program is complete.  This week, in-house staff are performing a test pit near 137 Brooks Street Boston in support of contract 6385 Pipeline condition assessment.  The work includes excavating approximately 6 feet by 8 feet pit to expose the pipe, cutting out a coupon, installing a closure piece of pipe, backfilling and paving

 

Sign up for electronic project updates through our Everbridge notifications service.

 

Follow us
twitter icon
flickr
YouTube button

Back to top

Updated: September 20, 2017
Original Post: September 12, 2017