Return to mwra.com home

Massachusetts Water Resources Authority
PROJECT UPDATE

Updated:

August 9, 2022

Contact:

MWRA Public Affairs


Wachusett Dam Bastion Improvements (Contract 7697)

image of location

About this Project:

Select Demolition, which consists of removal, cataloging, and storage of granite blocks, of the walls of the Bastion Building.  Re-installation of removed granite blocks.

  • Demolition and reconstruction of the roof of the Bastion Building.
  • Demolition, which consists of removal, cataloging, and storage of granite stair blocks, and re-installation of the granite stairs attached to the Bastion Building.
  • Demolition, which consists of removal, cataloging, and storage, of granite parapet wall blocks, and re-installation of the parapet walls around the roof of the Bastion Building.
  • Asbestos and lead abatement
  • Replacement of 2 aluminum windows
  • Miscellaneous crack repair

This $435,044 contract was awarded to to Kleinfedler Northeast Inc. Contract duration is approximately 15 months.

MWRA Contact:

If you have any questions please contact MWRA Public Affairs.

To receive electronic project updates, please register your email address with the MWRA Alerts Service, provided through Everbridge.

Project Updates:

August 9, 2029

Sign up for electronic project notifications andupdates through our Everbridge service.

Upcoming Work:

  • Removal of roof planks and beams
  • Removal, labeling and storage of Parapet blocks
  • Begin demolition of concrete walls

Floor installation and building supports

Floor installation

Removal of granite capstone at Stairwell

Removal of Roof and Abestos Mastic (bagged to keep the asbestos from spreading)

High winds caused scaffolding to fall apart but will be repaired

June 29, 2022

Work Completed:

  • Installed structural monitoring points
  • Removed windows and frames
  • Built enclosure around electrical equipment to remain
  • Installed engineer’s field trailer
  • Continued work on roadway improvements
  • Installed temporary fencing around project
  • Submitted demolition plan
  • Submitted electrical demolition plan
  • Shut down power to 13.8KV cable

Upcoming Work:

  • Injection grouting of wall cracks
  • Injection grouting of wall cracks
  • Install doka dance floor
  • Install interior wall shoring
  • Install support for cable tray
  • Begin removal of roofing topping slab

Installed filter sock

Installed floats for external scaffolding

Building work platform for external scaffolding

Installation of turbidity curtain

April 28, 2022

Project updates will be posted throughout the period of construction.


Follow us

twitter icon
flickr
YouTube button
Sign Up for Everbridge Notifications from MWRA